An automation company in Batu Kawan has orders for a batch of inspection machines. Its engineers design the cameras, the motion stages and the software, and those parts are the reason customers buy the machine. The welded base frame, the enclosure panels, the doors and the cable trays are also on the drawings. In a busy month, they are the parts that decide the delivery date.
Those parts are fabrication work. They can be made outside, as long as the drawing says clearly where the frame stops being structure and starts being part of the machine's accuracy.
What you'll learn
- Why Penang equipment builders are short of capacity
- Which parts of a machine suit a fabrication workshop
- Where the frame meets the precision parts
- What to send for a machine frame or enclosure
- What we will not do
Why Penang equipment builders are short of capacity
On 29 October 2026, Estek Automation opened a RM 20 million facility in Batu Kawan. The company designs and builds die sorters and wafer inspection systems, and it also assembles and integrates equipment for other companies. The new building has about 50,000 square feet of floor space. It is one example of a Penang company that has grown from designing machines into building them in larger numbers.
We have no connection with Estek. We mention the company only as an example of the equipment builders this article is about.
Earlier in October, Kenanga Research published notes from visits to equipment makers and machining companies in Penang and Johor. The analysts wrote that demand appeared to be arriving faster than some companies could respond. They also wrote that suppliers had turned to outsourcing to ease the pressure, and that even subcontractors were finding their capacity tight. Their view was that 2027 would be a stronger year than 2026, as new capacity comes into use.
When an equipment builder is short of time, its engineers should spend that time on the parts only they can make. A base frame or a set of enclosure panels takes workshop hours, floor space and welders. Those can be bought, provided the drawing is complete enough for another workshop to work from it.
Which parts of a machine suit a fabrication workshop
A typical piece of semiconductor equipment has a heavy base frame that carries everything else, often welded from tube or plate. On top of the frame there is an enclosure made of sheet-metal panels, doors and covers. It keeps people away from moving parts and keeps the inside clean. Inside, there are brackets, cable trays, guards around the motion stages and trays that catch small parts. Outside, there may be a monitor arm, a tower light bracket or a frame for a filter unit.
All of these are cut, bent, welded and finished. Most of them have tolerances that a fabrication workshop works to every day, because they must fit each other and the floor rather than locate a wafer. They are also the parts that change least between one machine and the next, so a batch can be made from one approved revision.
Small parts are worth sending too.
A bracket that is drawn quickly at the end of a design is often the part that holds up final assembly, because nobody ordered it until the frame arrived. If the brackets are made in the same order as the frame, they arrive together. Single-Source Fabrication: How Drawing-to-Assembly Under One Roof Cuts Project Risk explains why related parts are easier to fit when one workshop makes them.
The material also needs a clear decision. Many machine frames are painted mild steel or aluminium extrusion, while panels near a cleanroom may be stainless steel or coated sheet. If your frame is mild steel, please say so in the first email, and we will confirm whether we can make it.
Where the frame meets the precision parts
Welding puts heat into a frame unevenly, and as the weld cools it shrinks and pulls the metal with it. So after welding, a frame is slightly different in shape from the frame that was first tacked together. For a frame that only carries panels, the small movement does not matter. For a frame that carries a linear guide, a camera mount or a wafer stage, it matters a great deal. The precision part will copy any twist in the surface beneath it.
The usual answer is to weld the frame first and machine the mounting faces afterwards. The drawing should show those faces clearly, with the datum they are measured from and the flatness required. Everything else on the frame can then be made to normal fabrication tolerances. This keeps the cost down, because the workshop is not trying to hold a machined tolerance across a whole welded structure.
Please also decide who will machine those faces. If two workshops are involved, both need the same drawing revision and the same datum. The frame must also be drawn with extra material on those faces.
The same thinking applies to enclosure panels, at a smaller scale. A door must close, seal and line up with its neighbours. Please say which gaps and edges are visible to the customer, because those are the ones that will be inspected by eye. A panel that sits behind another panel can be judged only on fit.
What to send for a machine frame or enclosure
Please send one package per assembly, with a clear revision. For a frame or an enclosure, that package should include the following.
- The drawings: the 2D drawings with critical dimensions, datums and tolerances, and the 3D model if you have one.
- The machined faces: which faces are machined after welding, who machines them, and how much extra material to leave.
- The material and finish: the grade or alloy, and the finish, such as painted, powder-coated, brushed or bead-blasted. Tell us if you will finish the parts yourself.
- The cleanliness requirement: if the machine will work in a cleanroom, tell us the class and any rules on cleaning and packing. We will confirm what we can provide.
- The hardware: who supplies hinges, locks, inserts and windows, and whether we should fit them.
- The quantity: a first machine, a batch, or a repeating monthly order.
Cleanroom requirements are covered in more detail in What to Specify on Stainless Parts for a Semiconductor Facility. If the first frame is a prototype and the next ten will follow a revised drawing, see One-Off, Prototype and Repeat Work: How the Brief Should Change.
Please tell us the date your assembly team needs each part, not only the date the machine ships. A frame is needed first, but the panels can arrive later, and that difference often makes the batch easier to schedule.
What we will not do
We will not design your machine or change its drawing without your approval. If a drawing shows a feature that will be difficult to weld or to bend, we will tell you before we quote and suggest an alternative. The decision stays with your engineers.
We will not claim a tolerance or a cleanroom standard that your drawing requires until we have confirmed that we can meet it. We will also not describe ourselves as a supplier to any equipment company named in this article. Send the drawing package for one assembly, and tell us how many machines you expect to build.
Frequently asked questions
Why are semiconductor equipment builders in Penang subcontracting more work?
Which parts of semiconductor equipment can be subcontracted to a fabricator?
How do you keep a welded machine frame accurate?
What should I send to get a quote for a machine frame or enclosure?
Will you change my machine design?
Send us one assembly